Enhancements to the middle school included the 10,000 square feet gymnasium addition that also serves as a high winds shelter and a new science wing featuring six new classrooms and lab space.
The front addition of the building brought the office and administration areas to the front, providing a more secure entrance. A life skills suite for special education was created in the former office space.
During the design phase, a $300,000 issue was encountered that involved the building’s firewalls. With our preconstruction efforts, we found value engineering options to offset the entire amount with no charge to the district. Our team completed this project ahead of schedule and returned significant savings to the district to reinvest in their project.