This project involved the construction of a new one-story, 11,150 square feet emergency department. The facility includes 10 exam rooms, a resuscitation room, a triage room, and a CT scan room, designed to optimize emergency care and patient flow.
With a tight construction schedule and significant rough-in requirements for medical equipment, the team prioritized early coordination efforts including pre-hardware of doors to expedite the installation process and facilitate a smooth project completion. With over 100 medical equipment and furniture items to coordinate and install, meticulous planning and regular communication with equipment is required to ensure all components are delivered and installed on time. |
|||